Gaza Central Desalination Plant & Associated Works - Phase 1. Package nr. 1b-Southern main carrier system- Pumping stations and reservoirs sites.

  • Category
    WATER / WASTEWATER NETWORKS
  • Client
    PWA
  • Supervisor
    PWA
  • Funded By
    WORLD BANK
  • Region
    South Governorate / Khan Younis
  • From - To
    2023-06-22 00:00:00 - 2024-12-22 00:00:00
  • Value
    19,169,400.00$

Construction of 4 rectangular reservoirs with total capacity of 25,000 m³ with their main HDPE feeders, Central Pump station of 1,700 m³/h capacity including 8,000 m³ Water tank and other related structures and electromechanical works in addition to SCADA system managing at least 20000 signals.