Gaza Central Wastewater Project- Reconstruction Program (ER7-4) Rehabilitation Of PS 2 & PS 3
- 
                            CategoryPUMPING STATIONS, SCADA, PLC
 - 
                            ClientCMWU
 - 
                            SupervisorDORSCH INTERNATIONAL CONSULTANTS GMBH
 - 
                            Funded ByKFW
 - 
                            RegionGaza City
 - 
                            From - To2015-09-01 00:00:00 - 2019-06-01 00:00:00
 - 
                            Value900,000.00$
 
The project is implemented for two sewage Pump Stations PS2 & PS3 in GAZ.A City as Rehabilitation and Fully Reinstallation works
Pumping Station 2
The scope of work is to supply spare part of the following Item
- Lifting equipment - supply and installation
 - Ventilation - supply and installation
 - Screens
 - Standby generator 250 KVA
 - Mechanical spare parts
 - Electrical spare parts including supply and installation of PLC
 
Pumping Station 3
The scope of work is to dismantle, supply, install and commissioning the following
- lowing item
 - Screen
 - Dry well submersible pumps
 - Valves & piping
 - Ventilation system
 - Lifting equipment
 - Flow measurement
 - Instrumentation & control equipment
 - Electrical control panel
 - Electrical cabling
 - Standby generator
 - Fire extinguishers
 - Civil engineering materials and metalwork